| This article was featured in the 
Study: Area can support soybean crush
A feasibility study on Minnesota Soybean Processors' (MnSP) proposed
soybean crush in Brewster touts the project as financially viable,
but a producer survey shows more support is needed to get the project
off the ground.
MnSP is proposing construction of a $50 million, 70,000-bushel-a-day
soybean crush just north of Brewster. The new, farmer-owned cooperative
currently has an option on an 81-acre tract of land, MnSP Chairman
Bob Kirchner said.
In an interview Monday, Kirchner appeared optimistic about the
feasibility study, which covers everything from world markets to
local soybean meal consumption.
Perhaps the most positive statistic is the long-term return on
investment, estimated at 30 percent for normal market conditions.
Even at a five-year low in the soybean crush market, the return
would still be 14 percent, the study shows.
The figures are based on a funding formula of 50 percent farmers'
equity and 50 percent borrowed funds. At 50 percent equity, farmers
would need to invest about $21.5 million to get the plant started.
South Dakota Soybean Consulting Consortium, an entity of South
Dakota Soybean Processors (SDSP), conducted the feasibility study.
MnSP has modeled its plant after SDSP's 80,000-bushel-a-day plant
in Volga, S.D.
Kirchner said he was surprised at one finding of Pro Exporter Network,
a consulting firm hired to analyze the project in conjunction with
SDSP. With the MnSP soybean crush using 25 million bushels of soybeans
a year, the firm's computer-generated model shows a price improvement
of only 5.4 cents per bushel for area farmers - about half what
MnSP expected, Kirchner said. He said he was optimistic that the
actual price improvements would be higher.
Other findings of the feasibility study include:
* The initial plant would employ 36 people, not counting management.
* Expanding the operation to 140,000 bushels a day would cost $16
million, but also lower the per-bushel investment cost through improved
economies of scale.
* The plant would be built with identity-preserved processing capabilities,
but wouldn't do any IP processing in the near future due to a lack
of contracts, Kirchner said.
* The initial plant would produce 140,000 tons of crude soybean
oil a year. MnSP has proposed an oil refinery in the future, but
until then, "We're working toward getting an oil marketing
agreement to complete the marketing plan," Kirchner said.
While the study numbers look good in general, the results of a
farmer survey reveal a bigger challenge.
Around 7,500 surveys were sent out to soybean producers in late
September to gauge interest in the project. Only 714 responded,
with 559 expressing an interest in the project. Kirchner cited a
busy harvest season, lack of information and distance as reasons
for the poor response. In fact, response was high and mostly favorable
in Nobles, Rock, Murray, Cottonwood and Jackson counties, which
were more likely to hear about the project through local media,
he said.
Currently, MnSP is planning public presentations on the feasibility
study and setting a timeline for the project.
"All the infrastructure needs have been addressed ... and
they don't see any problems achieving the needed infrastructure,"
Kirchner said.
MnSP must eventually obtain a permit from the Minnesota Pollution
Control Agency. Kirchner said the co-op will apply for the permit
once an engineer's design is complete.
The feasibility study also states that "An effort between
MnSP and SDSP to form a joint alliance is proceeding in the early
stages." It goes on to state that the cooperatives share similar
philosophies and could save money through successful negotiations.
"At some point in time, it could lead to a management contract,"
Kirchner said.
TENTATIVE TIMELINE
For MnSP soybean crush
MPCA PERMIT APPLICATION: June 2000.
MPCA APPROVAL: April 2001.
CONSTRUCTION BEGINS: Sept. 2002.
PLANT STARTS OPERATION: Dec. 2002.
|