Soybean Prices
Our Beginning
Mission Statement
Press Releases
Stock Information
Board of Managers
Newsletter
Links
Resources
Contact Information
Home
 
BioDiesel Plant
BioDiesel Pricing Meal & Hull Prices Quality Premium Program
 
 

Construction Update
Week of June 20, 2005

The Biodiesel project appears to be on schedule for an August 1 st start-up.

Process piping in the biodiesel building is 100% complete with utility piping about 80% complete. All tanks have been set in place and piping to and from the process is in progress. The electrical conduit is complete and we have begun pulling wire.

In the Pre-treat plant all equipment has been set and contractors will move to this area as they are freed up from the biodiesel portion of the project. We have pre-treated oil on site for the biodiesel start-up as the pre-treat portion of this project will be three to four weeks behind the biodiesel plant.

 

 

 
 
  Send questions or comments about this web site to mnspwebmaster@mnsoy.com


Copyright © 2003-2008
All Rights Reserved


Web Site Designed and Maintained by:
MAS Media

Some photos used were provided courtesy of DuPont